ConstructSim Planner CONNECT Edition Update 5 Help

To Change the Appearance of a Task

  1. In the Schedule Panel section of the Animation Producer dialog, right-click the task whose appearance you want to change.
  2. In the dialog, click the Change Task Appearance icon.


    The Change Task Appearance tool settings window opens.



  3. From the Task option menu, select the task whose appearance you want to change.
  4. In the Start section, choose the element's color and transparency when the task begins.
  5. In the Finish section, choose the element's color and transparency when the task ends.
  6. Accept the changes with a data point.